-
Location
Near Annapolis, MD
-
Duration
September 2004 – May 2005
This project involved replacing the concrete overlay on four lane miles of the Chesapeake Bay Bridge (US 50/301) near Annapolis, MD. Between September and early November 2004, Wagman replaced 2.5 lane miles, allowing traffic restrictions to be removed in advance of cold weather. In April 2005, Wagman returned to the project to replace an additional 1.5 lane miles. A total of 2,440 cubic yards of Latex Modified Concrete (LMC) was used to successfully complete the new overlay.
Key Challenges & Project Details
- Replaced a failed micro-silica overlay
- 2,440 CY of Latex Modified Concrete
- Project required a quick response and completion timeframe