Location
Clarion, PA
-
Duration
July 2023 - February 2024
-
Owner
Pennsylvania American Water
-
Architect
Architectural Innovations, LLC
Wagman Construction partnered with Pennsylvania America Water, an ongoing client of Wagman’s since 2018, to work on constructing a new, 5,800 SF office building at their Clarion Water Treatment Plant in Clarion, PA. The scope of this $2.5 million project included construction and site work, which included utilities for the new building.
Key Challenges & Project Details
- To bridge the gap until the permanent mechanical equipment arrived, the project team implemented temporary heating.