Location
Norfolk, VA
-
Duration
Spring 2023 - 2026
Wagman Heavy Civil is a subcontractor for the Hampton Roads Connector Partners (HRCP) on the high profile, $3.8B Hampton Roads Bridge Tunnel Expansion project for the Virginia Department of Transportation (VDOT). Deemed the largest highway construction project in Virginia’s history, it includes widening of the current four-lane segments along nearly 10 miles of the I-64 corridor in Norfolk, VA and new twin tunnels across the harbor.
Wagman’s $9M scope of work includes roughly 7,500 CY of LMC that will be placed on 20 bridges, totaling 80,000 SY of deck. The main bridge on the project, the Willoughby Bay Bridge, consists of both eastbound and westbound bridges, each measuring 4,994 FT in length. Deep hydro-demolition is being performed on the bridge, with a latex depth of over 4”. The concrete compressive strength requirements are 3,500 psi in seven days and Wagman’s test batch results were 4,000 psi in seven days. This allows for traffic to be released within the seven day time frame.
Wagman’s portion of work extends into 2026.
Key Challenges & Project Details
- This is one of the largest furnish and place jobs that Wagman has received as a subcontractor.