    April 2013 – November 2013

The I-83 over US 30 Rehabilitation project in York, PA involved replacing deteriorated bearings and performing significant superstructure rehabilitation on I-83 over US 30. This $2.2 million project for the Pennsylvania Department of Transportation required phased construction and multiple traffic shifts to maintain two lanes in each direction and nighttime detours of I-83 to allow for superstructure bear replacement.

Key Challenges & Project Details

  • Bridge deck repairs: 870 SF
  • Concrete poured: 200 CY
  • Bearings: 45
  • Concrete: 160 CY
  • Work was performed in double shifts to meet project deadline.
  • Three project phases: right-hand lane of northbound I-83, right-hand lane of southbound I-83, and left-hand lanes of north and south-bound I-83

Project Fun Facts

  • The life expectancy of the new bearings is 30-40 years.