I-95 North of the Fort McHenry Tunnel to
I-895 in Baltimore, MD
Duration
November 2004 - November 2006
Description
Scarifying and latex modified concrete
overlay of 22 bridge decks, related bridge joint and parapet work,
steel repairs to bridges, sign structures and related miscellaneous
work.
Scarifying the bridge deck. Jackhammering is necessary where the scarifying machine cannot reach.